Power system A is operating in parallel with other systems and has a frequency bias of 50 MW/0.1 Hz. For a loss of generation in one of the interconnected systems resulting in a frequency drop of 0.02 Hz, system A should
provide 10 MW of support
provide 20 MW of support
not be affected
provide 30 MW support
provide 10 MW of support
provide 20 MW of support
not be affected
provide 30 MW support
Answer
Download EE MCQ app
Related Question
GETCO Exam Paper (30-11-2008)
Choose the word which is most nearly the OPPOSITE in meaning
SECURE
discover
offend
defend
endanger
discover
offend
defend
endanger
Answer
Download EE MCQ app
GETCO Exam Paper (30-11-2008)
Transfer of power between two power systems takes place with power flowing from the system with the
Lagging power angle
Higher input current
Greater leading power angle
Higher voltage level
Lagging power angle
Higher input current
Greater leading power angle
Higher voltage level
Answer
Download EE MCQ app
GETCO Exam Paper (30-11-2008)
Graded time lag over current relaying without directional features can be employed for protection of
none of these
radial feeders
ring mains
parallel feeders
none of these
radial feeders
ring mains
parallel feeders
Answer
Download EE MCQ app
GETCO Exam Paper (30-11-2008)
In an overhead transmission line, wave traps are used for the detection of the _____ signals.
fault current
fault voltage
fault power
carrier
fault current
fault voltage
fault power
carrier
Answer
Download EE MCQ app
GETCO Exam Paper (30-11-2008)
The planning Commission was set up in
April, 1947
March,1950
January, 1948
September, 1947
April, 1947
March,1950
January, 1948
September, 1947